Current Projects:
Plachy Hall Renovation & Addition - P0612
- New Construction 36,900 GSF (gross square feet)
- Renovation 35,400 GSF
- Work to include extensive controlled maintenance and updated Code deficiencies.
- Cost $10,194,684.00*
- Begin Construction early 3rd quarter 2007
- Complete Construction early 1st quarter 2009
- Architect - Christopher Carvell Architects
- Contractor - FCI Constructors
Roof Replacement on Various Buildings Phase 1 of 3 - M06052
- To replace a portion of roof on Plachy Hall.
- To be completed in conjunction with P06012
- Project Cost $673,116
- Architect - Christopher Carvell Architects
- Contractor - FCI Constructors
Water Distribution System - P0602
- Phase 1 to engineer Phase 2 & 3, $242,105
- Phase 2 to install a campus irrigation water distribution system supplied by a single source non-potable water source from the City of Alamosa. $953,016*
- Phase 3 (anticipated in 2008) to upgrade 50% of the irrigation system, provide and install a central control system. $919,509
- Engineer - Carter Burgess
- Bid Phase 2 late 2nd quarter 2007, Complete early 4th quarter 2007
- Bid Phase 3 late 2nd quarter 2008, Complete early 4th quarter 2008 (Funding not yet approved)
Coronado Fire Alarm Upgrades
- To upgrade Fire Alarm system in Coronado Hall
- Project Cost $187,000
- To bid late 2nd quarter 2007
- To complete Early 3rd quarter 2007
- Engineer - JCN Engineering
Marvell House Renovation
- To renovate the President's residence, 6,551 GSF
- Project Cost $426,500
- Architect - Slaterpaull Architects
- To Bid late 2nd quarter 2007
- To complete early 4th quarter 2007
Community Outreach Center Renovation
- To renovate the Old Art Building, 5,660 GSF
- Project Cost $521,000
- Architect - Slaterpaull Architects
- To Bid mid 3rd quarter 2007
- To complete early 2nd quarter 2008
Facilities Services Switchgear Replacement
- To replace antiquated electrical service in Facilities Services Building
- Project Cost $113,586*
*Indicates projects approved by the Colorado JBC, waiting on final approval of the 2007 Long Bill by signature of the Governor anticipated mid 2nd quarter 2007.
Total Anticipated Project Cost for 2007 = $13,311,007